Risk and Failure

Section 12

Risk and Failure

On this page

12.1 Continuous Risk Register #

Risk handling must be continuous, not a one-time assessment. One Risk Register must record every identified risk with an owner, an analysis, a mitigation plan, and a tracking method. A risk may be closed in exactly two ways: by mitigation, recorded with the evidence that the exposure is gone; or by acceptance, which requires the documented acceptance rationale of a named human. The two closures must never be recorded as one. Risks must be revisited at Gates (§8.3). [GP-61]

12.2 Failure closure by numbered corrective actions #

A failure must produce a formal report, at a formality scaled to the Criticality Class of what failed. The report must name the root cause or causes and a numbered list of corrective actions. The failure is closed only when every corrective action is verified and accepted by a human authority; where the failure is safety-significant, that authority must be independent of the Executor whose work produced the failure. Until closure, progression past the failed state is blocked. [GP-62; GP-40]